本文基于武汉市地铁二号线越江隧道工程周边地质环境条件和工程特点,采用灾害风险评估矩阵法(R=P×C)结合专家调查法对该隧道盾构掘进段施工可能存在的风险进行了分析和评价,评定出盾构进出洞、开挖面失稳等6个风险因素的风险等级以及对工程安全的影响程度,并根据评估结果提出了相应的风险对策和风险控制措施,以降低和控制盾构掘进段的施工风险。该研究可为类似工程提供借鉴及参考。
Abstract:Based on the geological conditions,surrounding environment and engineering characteristics of the river-crossing tunnel project,Line 2 of Wuhan Subway,this paper analyses the potential risks of construction in the shield driving period,and researches the risk level of six risk factors such as shied driving-in and driving-out and excavation face instability as well as their effects on the safety of the project by means of disaster risk evaluation matrix method(R=P×C) and expert investigation method.Finally,the paper puts forward the corresponding countermeasures for the risks so as to reduce and control the risk of construction in the shield driving period on the basis of the analytical results.The study can provide the reference to similar projects.
[1]卜庆,姚浩.上海某越江隧道盾构施工风险评估[J].上海建设科技,2007,(5):67-69.
[2]高峻,钱建文.庆春路过江隧道施工难度及风险的分析与控制[J].隧道建设,2006,26(5):34-36.
[3]刘凌云,杨德磊,郭海柱.隧道盾构进出洞施工风险分析[J].低温建筑技术,2010,(8):51-53.
[4]陈传灿,陈立生,彭少杰,等.西藏南路越江隧道施工难点和对策[J].科技导报,2009,27(19):28-32.
[5]崔玖江.盾构隧道施工风险与规避对策[J].隧道建设,2009,29(4):376-396.
[6]李国成,丁烈云.武汉长江隧道盾构施工引起的地表沉降预测[J].铁道工程学报,2008,(5):59-62.
[7]陈中.成都地铁盾构隧道施工风险分析及策略[D].成都:西南交通大学,硕士学位论文,2008.
[8]杜栋,庞庆华.现代综合评价方法与案例精选[M].北京:清华大学出版社,2005.
[9]肖龙鸽,王超峰,赵运臣.大直径泥水盾构施工引起的地表沉降分析和对策[J].现代隧道技术,2008,45(5):50-54.
[10]中华人民共和国建设部.地铁与地下工程建设风险管理指南[M].北京:中国建筑工业出版社,2007.
基本信息:
中图分类号:U455.1
引用信息:
[1]杨小伟,闫天俊,倪正茂,等.武汉地铁越江隧道施工风险分析与控制[J].安全与环境工程,2012,19(03):107-110.
2012-05-30
2012-05-30